Subject: Network Render. Does it use the host machine and dual processors?


Vile ( ) posted Wed, 12 September 2007 at 3:28 PM · edited Sun, 17 November 2024 at 1:31 AM

I am doing an image that is going to take a really long time so I thought I would do a network render seeing how I have two computer 1GHz and 1.4GHz along with a 1.87Dual core. But here is the rub. When I start the render on the dual 1.87 I can tell it is using both processors because of a little gauge. Now when i do the network render it seems to hardly hit either processor on the dual system which is the host.

Any ideas? Did I forget a setting to use the host computer?

AB


dhama ( ) posted Sat, 15 September 2007 at 4:51 PM

I think you have to run the render on the slowest machine when doing a network render like you are so that it takes advantage of the faster processors. Sorry if I don't have the full answer here, but try that at least and see if theres a difference.


Gog ( ) posted Mon, 17 September 2007 at 6:10 AM

Depends which version of Bryce you're on but there used to be 'render on host machine' tick box....

----------

Toolset: Blender, GIMP, Indigo Render, LuxRender, TopMod, Knotplot, Ivy Gen, Plant Studio.


Privacy Notice

This site uses cookies to deliver the best experience. Our own cookies make user accounts and other features possible. Third-party cookies are used to display relevant ads and to analyze how Renderosity is used. By using our site, you acknowledge that you have read and understood our Terms of Service, including our Cookie Policy and our Privacy Policy.